Its been a while (over 2 months in fact) since my last posting. Since then I have been on a short tour to Europe and Canada which I’d like to share with everyone. But before that, here’s a Mayapur TOVP update:
Govinda prabhu, one of our key construction managers, informed me that yesterday the construction company, Gammon, hammered in the 1,000th pile for the foundations (out of 2,600+). Things are going well, with the five pile drivers on site hammering away from 5:00 AM to 9.00 PM. Its a comforting sound, knowing that Srila Prabhupada’s biggest challenge to the western, materialistic science-based view of the universe is now underway.
Another milestone: yesterday the first above ground column was started, on the central area of the main temple. This is two months ahead of schedule. No photos since there isn’t much to see since the last posting.